Party wall agreements without the jargon
When you need one, what it costs, how long it takes, and what happens if your neighbour objects.
Separate from planning, and often forgotten
The Party Wall etc. Act 1996 is nothing to do with planning permission. You can have full permission and still be unable to start because you have not served notice.
When you need one
- Building on or at the boundary line
- Excavating within three metres of a neighbour's structure, below their foundation depth
- Cutting into, raising or removing a shared wall
Which covers most rear extensions on terraced and semi detached houses.
What it costs and how long
If your neighbour consents in writing, nothing but the notice. If they dissent, each side appoints a surveyor, or you share one, and an award is drawn up. Budget one to two thousand pounds per neighbour and four to eight weeks.
Serve early
Two months notice is required for most works. Serving at the same time as your planning application means the two clocks run together instead of one after the other.
Does this apply to your house?
Reading the rules is one thing. The Project Calculator applies them to your house and shows you the answer as a drawing, with the cost alongside.
Open the Project Calculator 60 secondsMore guides
GuidePermitted development rights, explained properly
What you can build without planning permission, what the limits actually are, and the traps that catch people out.
Read it →
GuideHow long does planning permission actually take?
The statutory eight weeks, what really happens, and where the time goes on a householder application.
Read it →
GuideYour planning application was refused. What now?
Why householder applications get refused, whether to appeal or resubmit, and how long each route takes.
Read it →
GuideArticle 4 directions, and why they matter to you
How councils remove permitted development rights, how to find out if yours is affected, and what it changes.
Read it →
GuideBuilding regulations and planning permission are not the same thing
Two separate approvals, two separate risks. What each one covers and why passing one does not help with the other.
Read it →Twenty minutes with the team that sweats the details.
No obligation, no script. An honest read on what your house can do, from people who obsess over getting it approved.
- Twenty minutes, by phone or video, whenever suits
- Anywhere in the UK, whatever your council
- You leave knowing what is possible, and roughly what it costs
Book your free call
Tell us where to reach you and we will confirm a time.
We confirm by email within one working day. No sales calls, ever. How we use your details.
That is booked in.
We will email you within one working day with a time.
What can I help with?
Planning permission, permitted development, what things cost, or what your council actually approves.
Guidance, not a lawful development certificate. For your house, use the Project Calculator.